The following photographs are pictures of the construction sequence for the Chesapeake, VA Carbon Burnout facility.The photos step through the 18 month process of building a CBO facility from the ground up. See similar pictures of CBO construction at Winyah,SC.
 |
| Greenfield CBO site |
| |
|
 |
| Preparing land for the new construction |
| |
|
 |
| Driving piles and dome foundation footer |
| |
|
 |
| Ringwall form for the storage dome |
| |
|
 |
| Fluid bed form work foundation |
| |
|
 |
| FBC pad poured and storage dome has taken shape |
| |
|
 |
| Lower section of FBC in place |
| |
|
 |
| Upper section of FBC in place |
| |
|
 |
| Starting structural steel construction |
| |
|
 |
| Structural steel construction topped out |
| |
|
 |
| Gas product cooler, hot cyclone set |
| |
|
 |
| Feed silo and process pipe bridge set |
| |
|
 |
| Loadout and Control Room building erection started |
| |
|
 |
| Process ductwork in place |
| |
|
 |
| Plant physically complete |
| |
|
|